Development Timeline
June 2007
Website launched and exhibition at Millennium Centre.
Website launched and exhibition at Millennium Centre.
Summer 2007
Submission of planning applications for sports facilities, Phase 1d and land east of Kings Warren.
Submission of planning applications for sports facilities, Phase 1d and land east of Kings Warren.
Autumn 2007
Submission of planning applications for Village Centre and Phases 4a, 4b, 5c, 6b and 6c.
Submission of planning applications for Village Centre and Phases 4a, 4b, 5c, 6b and 6c.
Spring 2008
Sports facilities and allotments complete and open for public use, construction begins on phases at southern end of Kings Warren.
Sports facilities and allotments complete and open for public use, construction begins on phases at southern end of Kings Warren.
Summer 2008
Commencement of construction at Village Centre, last phases of Kings Warren and infrastructure work for land east of Kings Warren.
Commencement of construction at Village Centre, last phases of Kings Warren and infrastructure work for land east of Kings Warren.
Spring 2009
Construction begins on first phases of land east of Kings Warren.
Construction begins on first phases of land east of Kings Warren.
Spring 2010
Village Centre and last phases of Kings Warren complete.
Village Centre and last phases of Kings Warren complete.
Summer 2010
Additional football pitches in land east of Kings Warren complete and added to existing facilities.
Additional football pitches in land east of Kings Warren complete and added to existing facilities.
Summer 2011
Redesigned balancing pond and new open space available for public use.
Redesigned balancing pond and new open space available for public use.
Summer 2013
Last phase of land east of Kings Warren complete.
Last phase of land east of Kings Warren complete.